Agnes Nolting Aquatic Complex

Project Milestones

Task NameDate
Zero Entry Play Structure InstallationFebruary 8-15, 2021
Pool Deck ConcreteMarch 23-April 12, 2021
Start Filling PoolApril 13, 2021 (dependent on any delays)
Perimeter Fence InstallationApril 13-26, 2021
Deck Equipment InstallationApril 27-May 3, 2021
New Pool Parking LotSpring 2021
Pool OpeningMay 29, 2021
*Project is weather and temperature dependent